§ 8209-5. Fees for drainage and sewer facilities.  


Latest version.
  • As a condition of approval of any subdivision, the tentative map for which is filed no sooner than 30 days after the adoption of any applicable drainage or sanitary sewer plan for a particular drainage or sanitary sewer area, the subdivider may be required to pay fees or consideration in lieu thereof for the purpose of defraying the actual or estimated costs of constructing planned drainage facilities for the removal of surface and storm waters from local or neighborhood drainage areas and of constructing planned sanitary sewer facilities for local sanitary sewer areas pursuant to the provisions of and subject to the conditions, powers and obligations set forth in Section 66483 of the Subdivision Map Act.