§ 8176-9.4.2. PEV charging station—Planned Development Permit.  


Latest version.
  • A Planned Development Permit is required for the following PEV charging stations:

    a.

    Direct current (DC) fast charging PEV charging stations.

    b.

    PEV charging stations not affixed to a building or structure and where the construction of the PEV charging station requires earth disturbing activities for which a grading permit is required.

    c.

    Repair, maintenance or upgrades to a permitted PEV charging where the proposed method of repair, maintenance or upgrade will involve substantial adverse effects on a coastal resource.

    Following approval of a Planned Development Permit, the permittee shall obtain a Zoning Clearance prior to initiating the permitted use in accordance with Section 8181-3.1.

(Ord. No. 4492, § 4, 6-21-2016)