§ 8176-9.4.3. PEV Charging Station Permit application requirements.  


Latest version.
  • When a Planned Development Permit and/or a Zoning Clearance is required, an application shall be filed with the Planning Division in accordance with Section 8181-5, and shall be signed by the owner and the applicant or authorized agent thereof. The application shall be processed pursuant to Article 11, Entitlements—Process and Procedures. In addition to providing the information and materials required by Section 8181-5, the application shall also provide the following information and materials:

    a.

    A site plan showing the dimensions of the parcel, location and size of any existing or proposed buildings or structures on the property, and adjacent streets and land uses.

    b.

    The location of off-street parking facilities, parking space dimensions, points of entry and exit for motor vehicles, and proposed charging system location including location of additional meter, if applicable;

    c.

    The proposed PEV charging station dimensions (height, width and depth).

    d.

    The method of attachment of the PEV charging station to any structure; if applicable.

    e.

    Single line electrical plan that graphically depicts points of connection from electrical source to PEV charging system.

    f.

    Type of charging system: Level 1, Level 2, or DC fast charging, with approved Underwriters Laboratories product listing agency verifying safety-related certification and inspection of the PEV charging system electrical devices and components.

    g.

    Manufacturer's specifications, installation guidelines, and, if applicable, ventilation requirements;

    h.

    Existing panel rating and proposed charging load and calculations;

    i.

    If a second electrical meter and dedicated breaker is installed for the purpose measuring only a PEV's energy use separate from a home or business electric load, the second meter must be labeled as "PEV Charging Only".

    j.

    Other information that the Planning Division may require to secure compliance with this Chapter.