§ 8175-5.20.11. Permit requirements.  


Latest version.
  • All new wireless communication facilities, except data collection units mounted on an existing utility pole (see Section 8175-5.20.4(b)), require a conditional use permit approved by the decision-making authority specified in Table 8174-5.

(Ord. No. 4498, § 3, 12-6-2016)